NEW QUESTION 34
Which chart types does the tabular planning table provide in SAP S/4HANA? Note: There are 2 correct answers to this question.

  • A. Work center capacities chart
  • B. Orders (dispatched) chart
  • C. Order (pool) chart
  • D. Capacity requirements chart

Answer: A,D

 

NEW QUESTION 35
Which SAP solutions are part of the Digital Value Network portfolio?
There are 3 correct answers to this question.
Response:

  • A. SAP Fieldglass
  • B. SAP Hybris
  • C. Concur
  • D. SAP Visual Enterprise
  • E. SAP Human Capital Management

Answer: A,B,C

 

NEW QUESTION 36
In the Schedule Production app, which settings can you make in the planning strategy? Note: There are 3 correct answers to this question.

  • A. Fixed pegging (on/off)
  • B. Planning mode (bucket/sequence)
  • C. Scheduling control (finite/infinite)
  • D. Direction (forward/backward)
  • E. Finiteness level (0...1)

Answer: B,C,D

 

NEW QUESTION 37
The SAP Kanban procedure could be used to trigger which of the following kinds of replenishment?
There are 2 correct answers to this question.
Response:

  • A. Vendor consignment
  • B. In-house production
  • C. Subcontracting
  • D. Stock transfer

Answer: B,D

 

NEW QUESTION 38
The pegging situation was changed because of an MRP heuristic run. What is a capability of dynamic pegging?
Response:

  • A. It replaces fixed pegging relationships unless they have been created for stock
  • B. It links receipts from an alternative location in case of a shortage in the default location
  • C. It propagates changed sales order priorities to the pegged planned orders
  • D. It enables the propagation of network alerts across the bill of materials structure

Answer: B

 

NEW QUESTION 39
The settings for MRP can be maintained at different levels. If settings have been maintained in different places, in which sequence does the system search for the MRP settings?
Please choose the correct answer.
Response:

  • A. Material Master -> MRP Group -> Plant Settings
  • B. Material Master -> Plant Settings -> MRP Group
  • C. MRP Group -> Material Master -> Plant Settings
  • D. Plant Settings -> MRP Group -> Material Master

Answer: A

 

NEW QUESTION 40
Mode selection is one of the scheduling options available in Advanced Planning in SAP S/4HANA. When can you use mode selection?

  • A. When multiple planned orders exists in one resource
  • B. When multiple production versions are maintained for one product
  • C. When multiple operations are maintained for one product
  • D. When alternate resources are used within one operation

Answer: D

 

NEW QUESTION 41
You want to procure your material components based on a forecast for the finished material derived from historical sales. When customers order, you produce the finished product and reserve it for that particular order.
Which is the appropriate planning strategy to use?
Please choose the correct answer.
Response:

  • A. Production by lot size (30)
  • B. Planning with final assembly (40)
  • C. Make-to-order production (20)
  • D. Planning without final assembly (50)

Answer: D

 

NEW QUESTION 42
Which options do you have to plan both quant ties and capacities during line loading in repetitive manufacturing? Note: There are 2 correct answers to this question.

  • A. Run MRP with automatic selection of production version.
  • B. Run PP/DS heuristics for repetitive manufacturing.
  • C. Run MRP with quota arrangement.
  • D. Assign planned orders manual lying the planning table.

Answer: B,C

 

NEW QUESTION 43
Which data model changes have been implemented in Sales and Distribution?
There are 3 correct answers to this question.
Response:

  • A. Elimination of output condition tables
  • B. Elimination of status tables
  • C. Elimination of LIS tables for rebates
  • D. Elimination of customer master tables
  • E. Elimination of document index tables

Answer: B,D,E

 

NEW QUESTION 44
Which material master setting is required to use the repetitive planning table for production with production orders?
Please choose the correct answer.
Response:

  • A. An overall profile be assigned on the Work Scheduling view
  • B. A repetitive manufacturing profile must be assigned on the MRP4 view
  • C. At least one valid production version must exist on the MRP4 view
  • D. The Selection Method must be set to "2 Selection by production version".

Answer: B

 

NEW QUESTION 45
If you use floats to limit dispatching in capacity planning, what type of time element can be reduced by strategy settings while dispatching?

  • A. Minimum wait time
  • B. Production time
  • C. Goods receipt processing time
  • D. Queue time

Answer: D

 

NEW QUESTION 46
What are the consequences if operation status Dispatched is set for a production order operation?

  • A. You can reschedule the operation using finite Scheduling in a planning board.
  • B. You can reschedule the operation using lead the scheduling.
  • C. You can reschedule the order using material requirements planning.
  • D. You can reschedule the order using lead time scheduling.

Answer: A

 

NEW QUESTION 47
A planner updated a production order status from partially confirmed "PCNF" to technically completed "TECO" by mistake.
What impact would this have to other users for this specific production order?
Please choose the correct answer.
Response:

  • A. The buyer can still see component reservations
  • B. The production manager can still see the capacity requirements
  • C. The warehouse clerk still carry out goods issue transactions
  • D. The production operator cannot enter additional confirmations

Answer: D

 

NEW QUESTION 48
When do you recommend the use of repetitive manufacturing?
There are 2 correct answers to this question.
Response:

  • A. High product stability
  • B. Low product complexity
  • C. High product complexity
  • D. Low product stability

Answer: A,B

 

NEW QUESTION 49
For which data objects do you have to set up CIF integration models in S/4HANA to use them in advanced planning?
There are 2 correct answers to this question.
Response:

  • A. Production plant
  • B. Work center
  • C. Material master
  • D. Contract

Answer: A,D

 

NEW QUESTION 50
Which of the following apply to MRP Live?
There are 2 correct answers to this question.
Response:

  • A. The sequence of planning materials is calculated across plants.
  • B. The definition of the planning scope is more flexible.
  • C. Planned orders need to be converted to purchase requisitions for externally procured materials.
  • D. The BAdIs for classical MRP also apply to MRP Live.

Answer: A,B

 

NEW QUESTION 51
Why would you use phantom assemblies? Note: There are 3 correct answers to this question.

  • A. To make the assignment of components easier
  • B. To reduce the number of changes required in bills of material
  • C. To increase the number of planning levels
  • D. To simplify the structure of bills of material
  • E. To reduce the number of material masters

Answer: A,B,D

 

NEW QUESTION 52
During planning you are facing an overload situation on a resource. Which activities do you consider to create a feasible production plan?
There are 3 correct answers to this question.
Response:

  • A. Use rescheduling with an alternative mode
  • B. Use optimization with respect to set-up times
  • C. Use multilevel MRP run for the products on the resource
  • D. Use a bucket-oriented capacity check
  • E. Use DS heuristic "Schedule Sequence"

Answer: A,B,E

 

NEW QUESTION 53
What Kanban status automatically posts goods receipt with reference to the procurement element?
Please choose the correct answer.
Response:

  • A. In use
  • B. Full
  • C. Empty
  • D. Wait

Answer: B

 

NEW QUESTION 54
The procurement type of your material is set to "E" for In-house production. Which of the following is valid to determine a source of supply in SAP S/4HANA?
Please choose the correct answer.
Response:

  • A. Selection Method
  • B. Production Version
  • C. Purchasing Info Record
  • D. Contract

Answer: B

 

NEW QUESTION 55
......